Project Update

The commissioning of the plant is in the final stages and our first polysilicon was produced in March 2017. There are 2 polysilicon trains under commissioning which will produce the 8,000 metric tonnes per annum. The 1.1MW solar farm is installed, reactors and converters completed, the control room is operational and we are making great progress as we transition to the operational phase of this state-of-the-art facility. 
01.jpg

First polysilicon produced March 2017

control-room
QSTec's modern control room
electrical room

Checking the electrical networks